Cross-Border Permit Date Change Notification
Verified from official sourcesSection 4.2(b)Version 1Effective -Verified 31 August 2026
In plain language
If you need to change the dates of your planned cross-border drone activity, you must submit the changes within 30 working days of your original application.
Requirement as structured
CAAS requires that any changes to the activity dates in a cross-border permit application must be submitted within 30 working days of the initial application.
Original regulatory text
Any change to the activity dates in the application should be submitted within 30 working days of the initial application.
Applies when
- operation
- Cross-Border