Cross-Border Permit Date Change Notification

Verified from official sources
Section 4.2(b)Version 1Effective -Verified 31 August 2026

In plain language

If you need to change the dates of your planned cross-border drone activity, you must submit the changes within 30 working days of your original application.

Requirement as structured

CAAS requires that any changes to the activity dates in a cross-border permit application must be submitted within 30 working days of the initial application.

Original regulatory text

Any change to the activity dates in the application should be submitted within 30 working days of the initial application.

Applies when

operation
Cross-Border