Reporting on corrective action implementation
Verified from official sources3.4 (5)AACR — Procedura P-AO-UAS-CAA, Capitolul 3 Supravegherea continuă a clubului sau asociație de aeromod, 3.4Version 1Effective -Verified 25 August 2026
In plain language
Clubs must update the AACR on their progress in fixing audit issues and provide proof that the corrective actions have been completed.
Requirement as structured
The aeromodelling club or association must inform the AACR regarding compliance with agreed remediation deadlines and submit objective evidence of the implementation of corrective measures.
Original regulatory text
(5) Club sau asociația de aeromdoelism este obligată să informeze AACR cu privire la respectarea termenelor de remediere a neconformitățiilor acceptate de AACR, și să transmită dovezi obiective cu privire la implementarea măsurilor corective.
Applies when
- operation
- aeromodelling club operations