Submission of corrective action plan after audit

Verified from official sources
3.4 (2)AACR — Procedura P-AO-UAS-CAA, Capitolul 3 Supravegherea continuă a clubului sau asociație de aeromod, 3.4Version 1Effective -Verified 25 August 2026

In plain language

If an audit reveals safety or compliance issues, the aeromodelling club must send a corrective action plan to the Romanian Civil Aviation Authority (AACR) within 15 days.

Requirement as structured

In case of non-conformities found during an audit, the aeromodelling club or association must submit a corrective action plan to the AACR within a maximum of 15 days from receiving the audit results.

Original regulatory text

(2) În cazul în care au fost constatate neconformități, în termen de maxim 15 zile de la primirea rezultatelor auditurilor/inspecȚiiilor de supraveghere, club sau asociația de aeromodelism transmite la AACR planul de măsuri corective.

Applies when

operation
aeromodelling club operations