Night EVLOS Operations Approval
Verified from official sources5.14Version 1Effective -Verified 25 August 2026
In plain language
To fly EVLOS at night, the operator must hold a specific night operations approval from CASA and comply with all of its conditions.
Requirement as structured
To conduct an EVLOS operation at night, the certified RPA operator must be approved for night RPA operations under instrument CASA 01/17 (or its replacement) and comply with its conditions.
Original regulatory text
For an approval of an EVLOS operation to be conducted at night, the certified RPA operator must: (a) be approved for night RPA operations under instrument CASA 01/17, or any replacement instrument in force from time to time unless the replacement instrument expressly applies otherwise; and (b) satisfy CASA that they can and will comply with the conditions of the instrument.
Applies when
- operation
- EVLOS